advertisement before-navabar

Power Supply

             
  • NEA: 6902 MWh
  • Private Sector: 9013 MWh
  • India: 4080 MWh
  • Tripping: 300 MWh
  • Demand : 20295 MWh
  • Soure : NEA
after_navbar

Tender deadline for feasibility study extended

   May 16, 2018        554        Kathmandu

The Nepal Electricity Authority (NEA) has extended the deadline to submit proposals to conduct a feasibility study and prepare a detailed design of the Tamor Storage Hydro Project since there were very few takers.

Only four firms had submitted proposals as of May 11, the original closing date for the global tender. The deadline has been lengthened by two weeks, the state-owned power utility said.

The NEA is mulling to build the plant with an increased installed capacity of 762 MW, a big jump from its original design of 200 MW. The DoED has given the NEA the go-ahead to build the Tamor project with an installed capacity of 200 MW, but the utility wants to ramp up the project’s installed capacity to 762 MW if the study report shows it is technically and financially viable.

However, if the storage project is built with the increased capacity, it will inundate the 37.5 MW Kabeli-A and 21.5 MW Lower Hewa projects currently being developed on the Tamor River, and the NEA will have to compensate their owners to abandon them. The department has clearly asked the NEA to first get the consent of the two projects that face being submerged in order to qualify for the license.

Sources at the NEA said they were negotiating with the promoters of the two projects, and that the deal would be wrapped up soon.

In 1985, the Japan International Cooperation Agency (Jica) had proposed building a 696 MW hydroelectric project on the Tamor River by building a 153-metre-high dam. However, the government did not show much interest in the proposal at that time.

The NEA management is now very keen on developing the project with the increased installed capacity. It believes that upgrading the Tamor project by paying compensation to the smaller schemes is a better option. If the plan materialises, the country’s energy production will see a massive jump, helping it to become self-sufficient in electricity generation and a net exporter.

From The Kathmandu Post

Feedback

web
analytics