Upper Solu Hydro Project Complete 30 Percent Construction

   August 22, 2018        1095   

Upper Solu hydro power project (30 MW) has been completed its 30 percent construction on Solu khola located at Solukhumbu district. This progress has achieved in around 18 months. Now, the dam side 70 percent work has been complete, the promoter Beni Khola Hydro Project Company has planed to set the target to start outlet tunnel after September this year.

Head works construction site.

Solu khola
Workers were involving for drill on bed rock for rock dowel at right bank flood wall.
Rebar and form work at flood wall panel-03 base slab.

Concreting work at right bank flood wall panel-03 base slab is continuing.

Headwords site.
Re-bar and form work at Intake walls.
Tunnel workers were involving for debris cleaning inside tunnel.
Mucking loader loading the mucking on mucking tripper inside tunnel.
Tunnel alignment.

Photo’s by: Beni Khola Hydro Project Company